Construction Update

Liona Tower is gaining new height! The concrete slab for the 19th floor will be completed this week, the walls on levels 5 to 14 are being framed, and 4th floor window installation has begun. 

As for Rycroft Tower, the concrete slab for the 6th floor is almost complete. The parking structure is also underway, as the foundation is being formed and poured.

Stay tuned to our newsletters and social media accounts for more updates on The Park on Ke`eaumoku’s construction progress and more.